Vatva Industries Association
Basic Infrastructure – Road And Water
INFRASTRUCTURE FACILITIES IN VATVA



INDUSTRIAL WATER SUPPLY
  • VIA has been operating G.I.D.C. Water Supply Scheme since April 2009.
  • Fresh Industrial Water supply to 2300 Industrial units through 72 kms pipeline with Bore wells.
  • 24 hours un-interrupted water supply with flat rate system as per the size of connection.
  • Upgraded under All scheme of Government of Gujarat.
  • Being maintained by Vatva Industrial Estate Infrastructure Development Limited.

DOMESTIC SOLID WASTE COLLECTION & DISPOSAL

LAST 5 YEARS INFRASTRUCTURE UPGRADATION REPORT

This report presents a comprehensive overview of the remarkable strides made in infrastructure development and maintenance within our industrial area over the past five years. These endeavours have not only enhanced our industrial community's quality of life but have also strengthened our commitment to a sustainable and prosperous future for our industrial stakeholders. Through meticulous project works and diligent maintenance efforts, we have laid the foundation for continued growth, productivity, and well-being within our industrial enclave. This report provides a detailed account of the key initiatives and achievements in our pursuit of a more resilient, vibrant and environment friendly industrial hub.

Here some details of projects are completed in GIDC Estate Vatva

A Project Works
Sr No. Description Phase Area / Length Unit
1 Rcc Road Upgradation 2 6250 RMT
2 Rcc Precast Swd Upgradation 2 4836 RMT
3 Street Light Network (210 Nos Run By Solar) 1 to 4 1749 NOS
4 Water Supply Network 1 to 4 95890 RMT
5 Suvarn Van (sv 1 To 8) + Road Side Plantation 1 to 4 193039 NOS

B Maintenance Work
Sr No. Description Phase Area / Length Unit
1 Asphalt Resurfacing With New Asphalt Roads 1 to 4 44870 RMT
2 CC Surface Drain 1 to 4 6305 RMT
3 Rcc Precast Swd 1 to 4 2962 RMT
4 Margin Area Paver Block and Road Junction 1 to 4 38420 SMT
5 Road Swiping By Two Team With 2 Nos Tractor And
Cleaning All Gidc Roads and Margin Area Everyday
1 to 4 Max 15 Labour Each Team EVERYDAY
6 Every Year Swd Cleaning In All Phase 1 to 4 32550 RMT
7 Domestic Solid Waste Collection (SWM) 1 to 4 200 MT/MONTH